Rinse the basin (8) and the water pump (18) with clean
water after use.

14. Transport (Fig. 23)

m Caution!
Disconnect power plug
Observe the following for transporting the stone cut-
ting machine:
• Lift off the roll slide (6) and transport it separately.
• Lock the cutting head unit (4).
• Empty the water tube (8) and cooling system.
• Fold the supporting feet (11) as described in (Fig.
4 - 7) and use the transport rollers for the transport.

15. Electric connection

The electrical motor installed is connected and
ready for operation. The connection complies with
the applicable VDE and DIN provisions. The cus-
tomer's mains connection as well as the exten-
sion cable used must also comply with these reg-
ulations.
Damaged electric connecting cables
Insulation damages frequently occur on electric con-
necting cables.
The reasons are:
• Pressure points, if connecting cables are routed
through window or door gaps.
• Kinks due to improper mounting or routing of con-
necting cables.
• Intersections due to overruns of connecting cables.
• Insulation damage due to pulling out from wall sock-
ets.
• Cracks due to ageing of insulation.
Such damaged electrical connection cables must not
be used and are life-threatening due to the insulation
damage.
Check the electrical connection cables for damage
regularly. Make sure that the connection cable does
not hang on the power network during the inspection.
Electrical connection cables must comply with the ap-
plicable VDE and DIN provisions. Only use connection
cables of the same designation.
The printing of the type designation on the connection
cable is mandatory.
AC motor 230 V~/ 50 Hz
• Mains voltage 230 Volt / 50 Hz.
• Mains connection and extension cable must have
3-wires = P + N + SL. - (1/N/PE).
• Extension cables must have a minimum cross-sec-
tion of 1.5 mm².
• The mains connection is secured with a max. 16A
fuse.

16. Maintenance

m Attention!
Disconnect the mains plug before carrying out any
maintenance work.
• Clean the machine after each work cycle.
• Replace worn out cutting discs.
• Replace damaged protection device
• Dust and pollution must be removed regularly from
the machine. The best way to clean the machine is
with a piece of cloth or brush.
• All moveable parts must be re-lubricated at peri-
odic intervals.
• Do not use any corrosive substances to clean the
plastic.
• The tub (8) and coolant pump (18) must be cleaned
regularly to remove dirt, as otherwise the cooling
of the diamond cutting disc (14) is not guaranteed.
• Re-commission and inspect all safety equipment.
• Maintenance and repair tasks may only be per-
formed by qualified personnel.
Connections and repairs
Connections and repair work on the electrical equip-
ment may only be carried out by electricians.
Please provide the following information in the
event of any enquiries:
• Type of current for the motor
• Motor data - type plate
Spare-part ordering
Please quote the following in your order for spare
parts:
• Type of device
• Article No. of device
• Ident. No. of device
• Spare Part No. of the required spare part
www.scheppach.com
GB | 35

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

59067089969

Inhaltsverzeichnis