18 | KTS 350 (KTS 3a Series) | Initial commissioning
4.
Initial commissioning
¶
Remove the KTS 350, the OBD connection cable, the
storage battery, the power supply unit with power
supply cable and the DVD drive with USB connecting
cable from the case.
4.1
Fitting the storage battery
¶
Insert the battery in the battery compartment and
secure by means of the two screws on the battery
(see fig. 3, item 3).
i
It is advisable to charge the storage battery for at
least three hours before running the KTS 350 off the
battery.
4.2
Port
Prior to the initial commissioning, make sure the mains
voltage matches the voltage specified on the power
supply unit (use the power supply cable provided).
4.3
Configuration of the operating
system
1. Supply the KTS 350 with voltage by way of the
power supply unit.
2. Switch on KTS 350.
3. After switching on for the first time, select the
Windows operating system language via the
language selection menu and follow the on-screen
instructions.
i
The on-screen keyboard can be opened in the "Ease
of Access Center" window (Icon
The Windows 10 start screen appears after some
time.
"
The adjustment of the Windows operating system is
complete.
|
1 689 989 293
2019-06-24
4.4
1. Start ESI[tronic] 2.0.
2. License ESI[tronic] 2.0.
i
ESI[tronic] 2.0 licensing is performed by way of a
file or online. Information on licensing can be found
in the ESI[tronic] 2.0 Online Help.
3. Restart ESI[tronic] 2.0 after licensing.
A firmware update is carried out.
"
Initial commissioning of KTS 350 is completed.
4.5
i
During a software installation always supply the
KTS 350 with voltage via the power supply unit.
i
See the installation instructions provided with
the respective software for additional information
concerning installation and update of the software.
).
ESI[tronic] 2.0 software licensing
Software installation
Robert Bosch GmbH