INSTALLATION

Before installing the unit, carefully read the safety instruc-
tions at the beginning of this manual; in particular read how
to set the unit in a STATE OF ZERO ENERGY and the

PRELIMINARY OPERATIONS.

1) Once the machine has been withdrawn from the
packaging, follow the instructions given in the
"GENERAL DELIVERY NOTES".
2) Position the unit on a horizontal surface.
Arrange the accessories as follows:
3) Insert the ring (b2) into the hollow in the filter holder.
4) Insert one of the two filters (b3 or b4).
5) Caution: danger of pollution.
DANGER OF POLLUTION
Tank Model
6) Open the hatch (11) and take out the reservoir (12).
7) Especially the first time, wash the reservoir with soap
and water. Fill the reservoir with water and make
certain that the outside of the reservoir is dry.
8) Return the reservoir (12) to its housing and close the
hatch (11).
Model for Direct connection to the water mains
6) Remove the tube from the hatch on the top part of the
machine.
7) Connect the shaped end of the Teflon tube to the
union on the base of the machine.
8) Connect the other end of the tube with the 1/8" union
to the mains water supply.
9) Make certain that the water drain tank (16) has been
inserted.
10) Two types of cup support grills (15) are possible:
a) tall cups.
b) normal cups.
Make certain that the cup support grill (15) is positioned
squarely and is level.
11) Make certain that the steam knob (8) is closed.
12) Make certain that the two buttons (1 and 4) protrude
and are not pressed.
13) Make certain that the line voltage corresponds to the
requirements indicated on the label.
14) Only if the steam valve (8) is closed, buttons (1 and 4)
are not pressed and the line voltage matches the label
requirements, plug the unit into the power supply
outlet.
15) The preliminary operations have been completed and
the machine is ready to be set up.

SETTING UP THE MACHINE

NOTE: if the sequence indicated below does not take
place, see the chapter entitled "TROUBLES-
HOOTING".
After having completed the preliminary operations:
1)
Make certain that the steam valve (8) is closed.
2)
Press the main switch (1) to turn on the unit; the
machine automatically feeds water into the boiler (ini-
tial time: approximately 3 min), once the water has
reached the set level, the units starts heating and the
heating light goes on.
Note: the machine has an electronic level valve so it
automatically feeds in water to the boiler as needed to
restore the level.
N.B.: the machine safety system shuts down the
machine after the pump has been running steadily
for approximately 2 minutes (this prevents the
pump from overheating). In this case, turn off
themachine by pressing the main switch and then
turn it on again.
While the unit is operating, the ON light (2) and the
heating light (7) are both lit.
3)
Wait until the heating light (7) goes off, indicating that
the water has reached the desired temperature.
4)
Note: if the water light (6) goes on, it means that the
water reservoir (12) is empty or nearly empty.
5)
Note: remember that to obtain a good drink it is best to
use the cup warming shelf (14) to keep the cups warm.
6)
At this point the machine has been set up and is ready
to make coffee or produce steam.
NOTE: At the start of the day's activities and in any case,
if there are any pauses of more than 8 hours,
then it is necessary to change 100% of the water
in the circuits, using the relevant dispensers.
NOTE: In case of use where service is continuous, make
the above changes at least once a week.
17