Commissioning
4
Commissioning
4.1
Function check
Prior to commissioning, please ensure that:
• The device has been mounted correctly
• The electrical connection is correct
4.2
Switching on the device
Once the final checks have been successfully completed, it is time to switch on the supply
voltage. The device is ready for operation after approx. 18 seconds!
Normal measuring mode commences as soon as the switch-on procedure is completed. Various
measured value and/or status variables appear on the display.
4.3
Display and operating elements
4.3.1 Display
Fig. 8: LC display of the field transmitter (illuminated, can be plugged in in 90° steps)