. COMMISSIONING
.1 MECHANICAL SET-UP
Note the following points when setting up the UPS system and its external battery
units (special accessories):
The contact surface must be smooth and level. It must also be su iciently strong
and sturdy to avoid vibration and shock loads.
Make sure the mounting is able to support the weight: This is particularly
important in conjunction with external battery units (special accessories).
Set up the units so that adequate air circulation is assured. There must be at
least 100 mm clearance at the back for ventilation purposes. Do not block the
intake openings on the front and, if present, on the side of the unit. There must
be a gap of at least 50 mm here.
Set up external battery units (special accessories) to the side of the UPS system.
To ensure the greatest possible mechanical stability, you should not set up the
external battery unit(s) above or below the UPS system.
Avoid extreme temperatures! We recommend an ambient temperature of 15 °C
to 25 °C in order to maximise the service life of the batteries. Do not expose the
units to direct sunlight or operate them close to other heat sources such as
radiators.
Protect the units against external e ects in particular moisture and dust .
If you transport the unit from a cold room into a warm one, or if the room temperature
suddenly drops then condensation may form inside the unit.
To avoid any damage due to condensation, leave the unit to acclimatize for 2 hours
before you switch it on.