3.2 PACKAGE CHECK UPON ARRIVAL

If no external damage is evident on the package upon its arrival, open it and check that all the components are
inside. If the package has suffered from rough handling, bumps or crashes, the carrier must be informed about
any damage; moreover a detailed report on the extent of the damage caused to the machine must be filled
within three days from the delivery date shown in the shipping documents. Do not overturn the package!! When
the package is transported, make sure, the box is lifted by the 4 corners (parallel to the ground).

3.3 PACKAGING DISPOSAL

The components of the packaging (carton box, pallets, plastic straps and polyurethane) are urban solid waste;
therefore they can be easily disposed. If the slicer is to be installed in countries where specific regulations are in
force, packaging must be disposed in compliance with them.

4. INSTALLATION

4.1 SETTNG UP ON THE SLICER

The slicer must be installed upon a working table suitable for the slicer's overall dimensions shown in Table 1-2-
3 (according to the model); therefore it must be adequately large, well levelled, dry, smooth, resistant, stable
and placed at a height of 80 cm from the ground.
Moreover the machine must be installed in a room with max. 75% not saline humidity at temperature between
+5°C and 35°C; that is to say in a place that does not provoke the slicer failure.

4.2 ELECTRIC CONNECTION

The slicer is equipped with a power supply cord and a VDE PLUG.
Connect the slicer with 230V/50Hz power source. Check that the earthing is fully operational.
Moreover check that features on the rating plate – serial number correspond to the features shown in the
consignment and delivery note.
Sense of blade rotation
Rating plate – serial number
If the direction of rotation is wrong, reverse two of the
three power supply cords in the plug or in the socket.