Lift configuration and venting (free lift)
1. All valves should be closed!
2. Selector switch on wheel-free lift!
3. Open connection on the main cylinder (accelerated hose, Drawing A-2)!
4. Carefully press the lifting button and watch until hydraulic oil comes out of the
accelerated hose!
5. As soon as the air has been released from the line and hydraulic oil appears, close the connection!
6. Raise the main scissors from the wheel-free lift and leave in end position
7. Open valve C!
8. Open bleed valve on secondary cylinder!
9. Open connection hose to the main cylinder (opposite side)!
10. Carefully press the lifting button and watch until hydraulic oil comes out of the bleed valve from the
secondary cylinder!
11. As soon as the air has been released from the bleed valve on the secondary cylinder and hydraulic oil
appears, close the connection!
12. Keep carefully pressing the lifting button and watch until hydraulic oil comes out of the
connection hose to the main cylinder (opposite side)!
13. As soon as the air has been released from here as well and hydraulic oil appears, close the connection!
You can start by equating the guide rails from the free lift via the valve.
A test of the main and free lifts under load can be carried out as a final step while continuously
observing the lifting platform and load.