9. Limit switch installation
a. Raise the lift up to the maximum height (see technical data).
b. Install the limit switch (1) on the elbow and adjust this using suitable nuts so that the limit
switch is activated in this position.
c. Carry out a function test for the limit switch.
d. Lower the lift to a height of 400 mm above the floor.
e. Install the CE stop (2) on the scissors and adjust the shutdown arm so that it is activated in
this position.
f. Carry out a function test for the CE stop
10. Final function check
a. Check the strength of the safety anchors
b. Check synchronisation and light barriers
c. Check function of limit switch
d. Acoustic warning signal when the CE stop is reached
e. Oil level check
f. Lift a load of approx. 2,000 kg to a height of approx. 1,000 mm
g. Lower the load to the first catch (approx. 500 mm).
h. For further lifting, check the synchronisation and adjust this again if necessary.
i.
Lower the load and assemble the missing covers
11. After the set-up process, fill in the attached inspection log.
This information is needed in case of service.
We recommend carrying out cavity sealing for optimum corrosion protection. Suitable
silicone must also be used for the joints.
® Copyright ATH-Heinl GmbH & Co. KG, All rights reserved / Misprints and technical changes reserved / As of: 2020-03
Manufacturer ATH-Heinl GmbH & CO.KG
- 34 -

Werbung

Inhaltsverzeichnis
loading

Inhaltsverzeichnis