Assembly
General
Notice
Safety instructions
Stop
Personnel qualification
Assembly work on the HAWA-Frontslide 60/matic may only be performed by properly authorised personnel.
To qualify as authorised, personnel must meet the following requirements:
• Training in construction fitting, or corresponding practical experience;
• The safety instructions in the operating instructions must have been read and understood.
Assembling the sliding shutters
Top track
The top track is fitted first, horizontally.
Bottom guide
The bottom guide and top track must be fitted exactly in parallel with each other.
Subject to modification
Hawa AG CH-8932 Mettmenstetten www.hawa.ch Tel. +41-1-767 91 91 Fax +41-1-767 91 78
– Frontslide 60/matic
Assembling the HAWA-Frontslide 60/matic is a multi-step process that must be
performed in the order described to ensure proper functioning of the finished
installation.
Risk of falling
Work on a building façade involves a risk of falling!
Assembly personnel must either be properly secured against a fall, or work
on professionally erected scaffolding.
Failure to observe this instruction may result in severe injury or death.