Installation and start-up
6.2
Start-up
1.
Put the reservoir bottle into the pressure tank.
2.
Put on the cover and screw up using the locking screws, ensuring that the riser pipe
reaches up to the bottom of the bottle.
3.
The metering unit can now be connected with the compressed air network.
4.
Use the tank pressure regulator to set the pressure required for the delivery of the
metering medium. The pressure depends on the viscosity of the metering medium.
5.
As soon as the metering medium emerges from the tip, feed a further quantity of
approx. 1 cm3 glue.
6.
For 'drip' discharge, change the applicator unit over to the automatic operating mode
and set the drop size by changing the application time.
Guideline values:
Data
Viscosities of up to 150 mPa/s (cp)
Viscosities of up to 2000 mPa/s (cp)
417101357 Rev. 4-02.2020
When the unit is being filled for the first time, make sure that the
metering medium reaches the application tip without forming any
bubbles. Therefore the metering valve must be held vertically
upwards, while the 'MAN' switch or the foot switch (in continuous
operating mode) is simultaneously operated.
26
Value Unit
0,02 (0,2) MPa (bar)
0,02 (0,2) -
MPa (bar)
0,08 (0,8)