SMA INVERTER MANAGER Installationsanleitung Seite 5

Vorschau ausblenden Andere Handbücher für INVERTER MANAGER:

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

SMA Solar Technology AG / SMA America, LLC
3.3.3 Connecting the Inverter and
Router via Ethernet
Pin assignment of network ports (LAN1 and LAN2):
8
1
1
8
Pin
Assignment for
10/100 Mbps
1
ETx+
2
ETx-
3
ERx+
4
---
5
---
6
ERx-
7
---
8
---
3.3.4 Connecting the I/O Box and
Weather Station (Optional)
Pin assignment of the serial interface (RS485):
1
2
3
6
7
8
Pin
1
2
3
4
5
6
7
Installation Manual
Assignment for
1,000 Mbps
TRD(0)+
TRD(0)-
TRD(1)+
TRD(2)+
TRD(2)-
TRD(1)-
TRD(3)+
TRD(3)-
4
5
9
Assignment
---
---
DataB(+)
DataA(-)
GND
---
---
Pin
8
3.3.5 Connecting the
Inverter Manager to the Voltage
Supply
Danger to life due to electric shock from touching
an ungrounded product
Touching an ungrounded product can cause a lethal
electric shock.
• Ensure that the product is integrated in the existing
overvoltage protection.
• Ground the enclosure of the product.
Procedure:
To connect the Inverter Manager to the voltage supply,
perform the following actions in the specified order.
• Connect the grounding conductor to the
Inverter Manager.
• Connect the power supply unit.
Connecting the Grounding Conductor to the
Inverter Manager
Shielded ground: The shielded ground (also called
"protected ground") is located at the pin connector for the
electrical connection in the displayed view.
Procedure:
• Ground the Inverter Manager. For this purpose,
connect the grounding conductor to the grounding
screw of the Inverter Manager. Proper grounding and
the correct cable route help limit possible interference
emissions due to electromagnetic interferences (EMI).
3  Inverter Manager
Assignment
---
IMVIOBOX-IA-xx-10
5