15. COMMISSIONING

 Make sure all transport stabilizers were removed.
 Check that all compressed air hose connections are correct. (see chap. 12)
 Check correct connection to the mains (see chap. 13).
 Check the circuit breaker position, it must be in the "I" position. If the main switch (2) is in the "0"
position, turn it to the "I" position.(Fig. 23).
 For cabinet-mounted compressors, turn the main switch (4) on the front side of the cabinet into
the "I" position; a green indicator indicates the equipment is in operation. (Fig. 23).
 Check connection of the cabinet connector to the compressor (Fig. 13).
 Check the connection of the display at the front door of the cabinet.
 Check connection of the cabinet manometer hose to the pneumatic block of the compressor (Fig.
9).
 Check to ensure the hose from the automatic condensate drain is connected to the collection
vessel. (Fig. 10)
 Configuring the language on the dryer display (see chap. 20.2).
 Configuring the date and time on the dryer display (see chap. 20.3).
 Check the drying mode settings (see chap. 20.4).
The compressor is not equipped with a backup power supply.
NP-DK50 4VR 50, DK50 2x4VR 110-AD-1_03-2022
46
INSTALLATION
03/2022

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Dk50 2x4vr/110/m

Inhaltsverzeichnis