The frequency of lift cleaning depends, among other
things on the frequency of use, of lift handling, of work-
shop cleanliness, and the location of the lift. Furthermore,
the degree of contamination depends on the time of year,
the weather conditions and workshop ventilation. Under
adverse circumstances, weekly lift cleaning might be re-
quired, however a monthly cleaning may be sufficient.
Do not use and aggressive and abrasive materials for
cleaning, rather use mild cleaners, e.g. a commercially
available detergent and lukewarm water.
• For cleaning, do not use high pressure washers (e.g.
steam cleaners).
• Carefully remove all contamination with a sponge, or if
required with a brush.
• Make sure that there is no residue of the cleaner on the
lift.
• Rub the lift dry with a cloth after cleaning.
8

Assembly and commissioning

8.1 Set up guidelines

• Lift set up is done by trained manufacturer personnel or
a contract partner. If the operating company has appro-
priately trained assemblers, the lift can also be set up
by them. Set up is to be done according to the assembly
instructions.
• A standard lift may not be set up in explosion endan-
gered spaces or wash halls. (It is necessary to consult
with your dealer).
• Before setting up, verify that there is a sufficient foun-
dation or make it according to the guidelines in the
foundation plan. The set up location must be level and
even. Foundations in open air and spaces where winter
storms or frost are to be expected, must have a founda-
tion to frost depth.
• An on-site electrical connection of 3 ~/N + PE, 400V,
50Hz is to be provided. The supply is to be secured
on-site with 16 ampere fuses. The connection point is
located on the operating boxes.
• To protect the electrical cable all cable conduits are to
be fitted with cable sleeves or flexible plastic pipes.
8.1.1 Set up and anchoring the lift
i
Before setting up the lift, ensure that everything possible
is done to prevent accidents due to careless assembly.
This includes, above all, the use of safe auxiliary means
(e.g. cranes, forklifts and a sufficient number of peo-
ple), diverse supports and a sufficient barrier to prevent
unauthorised access.
• Carefully remove the lift from the wooden crate and
check for damage.
• Position and align the lift columns according to the data
sheet at the desired set up location.
• Guide the supply line to the operating column (on-site).
OPI_POWER LIFT HDL 6500 SST DG-7000 SST DG-8000 SST DG_V4.0_DE-EN-FR-ES-IT
• Connect the electrical cables and measurement cables
to both columns.
• Check the position of the lift again.
• Fill with approx. 17 litres of clean hydraulic oil into the
oil container of the unit.
• Holes for floor anchorings are to be placed through the
holes in the base plates. Clean the bore holes by blow-
ing them out with air. Guide the safety anchor into the
drilled holes but do not fasten them yet.
The lift manufacturer recommends Liebig safety anchors
or similar anchors from other reputable anchor manu-
facturers Hilti, Fischer (with approval) while following
their conditions. Information can be given from your
anchor suppliers.
• Before anchoring the lift, check whether the load-bear-
ing concrete is of quality min. C20/25 up to the finish-
ing level of the completed floor. In this case, take the an-
chor length from "anchor length without floor covering".
If there is a floor covering (tiles, screed) on the load
carrying concrete, the thickness of this covering must be
determined and the anchor length selected according to
"anchor length with floor covering".
• Briefly push the "Lift" button. Consider the rotation direc-
tion of the motor.
• If the lift rail does not lift, the rotation direction of the
motor must be checked again and if required two
phases of the power supply must be exchanged. (only
for 3-phase AC supply).
• Check the precise vertical set up of the lift columns and
if required make sure there is a suitable support (panel
strips) that make contact with the floor.
To prevent vertical oscillations of the column, it is neces-
sary to position the support in the middle and not only
on the edge of the base plate.
• Tighten the anchor to the required torque (see the condi-
tions of the anchor manufacturer).
Each anchor must be tightened to the re-
!
quired torque. Safe operation and stability
of the lift are not guaranteed with a lower
torque.
• If required, do a reset before first operation. (see Sec-
tion 6.3).
• Raise the lift approx. 800 mm.
• Mount the lifting arm. Secure the bolts with the locking
rings.
• The lift must be moved to the "lift" and "lower" end po-
sitions without a vehicle.
• The safety devices must be checked.
• Move the lift with the load into the end position several
times. (see Section 5.1).
• Check the hydraulic lines again for leak-tightness.
• Check the anchor fastenings again.
i
In case of malfunction, firstly inform customer service.