NOTE:
The service life of the Conel Stream is highly dependent on the water quality.
Inspections may be carried out independently or by professional/knowledgeable
personnel or by the manufacturer;
Maintenance and repairs may only be carried out by professional and knowledgeable
personnel or by the manufacturer.
This professional shall have read and understood this operating manual;
The notes and periods in the table are indicative and must be adapted to the respecti-
ve local and outdoor environments.
Plant part/de-
Measure
vice
Filter
Inspection
Maintenance Cleaning the filter
Pump
Inspection
Maintenance Rehearsal:
Drinking water
Inspection
re-feeding
Pipelines
Inspection
Wastewater
Inspection
lifting plant
(if available)
Maintenance Check for tightness, function, control of
Removal valves
Inspection
Rinsing equip-
Inspection
ment
(Toilets)
Marking
Inspection
Implementation
Control of the condition
Visual check for function and tightness
¾ Before, during or after the test run,
check:
¾ The electrical protection of the system in
accordance with VDE regulations
¾ Preprint of the MAG (if available)
¾ Tightness of the pump's sliding ring seal
¾ Function of the setback preventer
¾ Pump and flow noise
¾ Tightness of the system and fittings
¾ Cleanliness of the plant
¾ Corrosion of plant parts
Check of the safety distance (water level
adjustment), the inlet valve and the overflow
when the inlet is fully open
Check all visible cables for condition, tight-
ness, fastening and external corrosion
Testing for operational capability, tightness,
external corrosion
level switching, adjusting heights of on, off
and alarm level check, control of the reflux
preventer for tightness
Checking all removal valves for tightness
and possible changes in water, odor, paint or
suspended matter.
Examination of the rinsing process of rinsing
devices (flushing boxes, press sinks), if
necessary correction of the rinsing water
volume.
Testing of the marking of all pipelines and
sampling points
75
Period
approx. 1 year
approx. 1 year
approx. 6 months
approx. 1year
approx. 1year
approx. 1year
approx. 1 months
approx. 6 months
approx. 1year
approx. 1 year
approx. 1 year