Operation
6.6

Lifting, Transport and Installation (manual operation)

1.
Position the device directly above the load. Avoid pulling it diagonally, make sure the load is evenly distributed.
2.
Place the device onto the load.
3.
Switch the device on using the main ON / OFF switch.
4. The load is now sucked.
5.
Look at the pressure gauge. As soon as a vacuum of -0.5 bar is reached, you can lift the load. On no account lift it
earlier, as the load would fall off.
When lifting, make sure that only one part at a time is being lifted! Carefully release any bits left hanging on with a
screwdriver before lifting the load any further.
Do not remove any bits with your hands, risk of crushing!
6. Now transport the device with the sucked load to the destination point.
7.
Lower the load and place it on clear, even surfaces, so that the load does not slip or tip.
8. Switch off the diaphragm pump using the main ON / OFF switch.
Caution! Once the machine is switched off, the suction lead is automatically bled and so the vacuum
disappears. Always keep feet well away from the danger area!
6.7

Tile laying

Recommended device configuration:
VPH basic device+
VPH-RS wheel set+
VPH-RS-AS, height adjustable stop, to put the tile in different angle positions, tilted to the front.
Example for tile laying
52710008/52710009
17 / 24
Only with the height adjustable stop VPH-RS-AS loads can be sucked in eccentrically.
Otherwise the load can become detached or break!