Commissioning
2.2 Mounting the Flowmeter
①
I/O Terminals TB1 and TB2
②
Input Power Connector P1
③
Fuse F1 Type GMA, 2A
④
Power Input/Fuse Cover
⑤
Power Cables
Figure 3-1
Input Power Connection P1 (Power Input/Fuse cover shown removed)
7. Replace Power Input/Fuse Cover and tighten setscrew.
8. Connect the power cables to the appropriate power source (100-240 VAC @ 50/60 Hz or
Note
The branch circuit must be limited to 20A. It is recommended that the circuit breaker be
located near the flowmeter.
9. If unit is operational, turn power off, replace Keypad Enclosure cover using six #8
12
9-36 VDC) and power up unit.
securing screws (torque to 7 oz-in). Reinstall transducer cables.
⑥
Data/Control Cables
⑦
1012CN Series Transducer Cables
⑧
Fill boots with CC110 to ensure weather tight
connection (supplied)
⑨
J1 RS-232 Port DB9 Connector
⑩
Keypad Enable Switch
SITRANS FUS1020 IP65 NEMA 4 Quick Start
Operating Instructions (Compact), 4/2009, CQO:QSG006 Revision B