connected to the charging station. There is no authentication via RFID cards.
To activate free charging and thus deactivate authentication, please proceed as follows:
1.
Either open the web interface and log in as described in section 6.3.1 or open the CP-Tool app
as described in section 6.3.2.
2.
Click on "Charging mode" or "Authentication mode" and set it to "Plug & Charge".

6.5. Grid-friendly control

Charging processes of the EM2GO Pro Power G2 EV chargers can be controlled by closing a potential-free
contact. This is necessary, for example, for charging stations from 4.2kW upwards, so that the electricity
supplier can interrupt the charging process or reduce the power by closing a contact via a control device such
as a ripple control receiver.

6.5.1. Connecting the cables

Risk of electric shock
Ensure that the power cable is not connected to the mains when working on the charging station!
Proceed as follows to connect the cables from the control unit to the EV charging station.
1.
Disconnect the charging station from the power supply.
2.
Open the decorative cover and the sealing cover as shown in Figs. 5-6 and 5-7.
3.
Feed the two cables from the power supply unit's control unit through the housing of the EV
charging station.
4.
Locate the two unused terminals marked + and - on the lower circuit board of the EV charging
station (see Fig. 6-7).
5.
Connect the two cables from the control unit to the two terminals.
6.
Set the jumper on the left side of the circuit board from position 1-2 to 2-3.
7.
Close the sealing cover and the decorative cover of the charging station.
8.
Connect the charging station to the power supply.