Important note: According to § 19 NAV in Germany, the operation of charging facilities for electric
vehicles must be reported to the responsible electricity supplier before use (from 11kW) and before
installation (from 22kW). This can also be done by the commissioned electrician. Please contact
your electricity supplier for further information. Please observe local regulations.
5. Setup and operation
5.1. Setup
5.1.1. Attaching the metal bracket to the wall
Note: It is recommended to install the charging station in a well-ventilated location, out of direct
sunlight and protected from wind and rain. To ensure good ventilation, you should mount the
charging station vertically and leave sufficient space, as shown in Fig. 5-1.