28 - COMMISSIONING

- You can now restart the equipment and check that it is operating correctly.
- Check the safety components.
It is recommended to note the operating readings (table below) for the equipment, indicating the serial number and all other required 
data that appears on the identification plate. This enables the system efficiency to be checked and faults prevented.
CL2 operating readings
System start-up date:
Serial No.:
Installer:
Site of installation:
Model: 28
35
50
65
75
Compressor
Air-cooled condenser
Nominal voltage
Voltage at terminals
Motor(s) input current
Mechanical inspection: tubes, fastenings.
Electrical connection tightness check
Clean the coil
Control check
74
Suction pressure
Intake temperature
Condensation pressure
Condensing temperature
Gas inlet temperature
Liquid outlet temperature
Air inlet temperature
Air outlet temperature
bar
°C
bar
°C
°C
°C
°C
°C
V
V
A
Date/Time