The unit must be lifted with the utmost attention and care
following lifting label instructions; lift unit very slowly, keeping it
perfectly level.
Positioning and assembly
The unit must be mounted on a level base of concrete or steel
and must be positioned so as to provide space maintenance
unit at one end, to allow removal of the tubes of the evaporator
and condenser. The space required is equal to 3,2 m. The
Figure 3 - Lifting the 2 compressors unit
(Lifting method is the same for 1 compressor unit)
tubes of the condenser and evaporator are expanded inside
the tube plate to allow the replacement, if necessary. The
space of the other sides including the vertical axis is 1,5 m.
The unit must be installed on a robust and perfectly level
foundation; it might be necessary to use weight distribution
beams.