Unit installation

Slightly tighten the two hoisting slings.
F

6.4 CENTER OF GRAVITY

a
d
e
b
Front side of unit
HP
8
Net weight
215
Gross weight
230
7 UNIT INSTALLATION
7.1 PRELIMINARY CONDITIONS FOR POSITIONING OF OUTDOOR UNIT
Mount the outdoor unit in a shady location or where it will not be
exposed to direct sunlight, or to high temperatures. It should also
be a well-ventilated spot.
Mount the outdoor unit so that noises and the discharge of air
from the unit will not bother neighbours or the surrounding envi-
ronment.
Install the outdoor unit in an area of limited access to the general
public.
In cold climates, ice may form on the unit. When installing the
unit, make sure that ice falling off the unit could not pose a risk to
passers-by.
When installing the outdoor unit in areas covered by snow, mount
the covers supplied by the fitter on the top of the unit and on the
heat exchanger inlet side.
Do not install the outdoor unit in zones where dust or contamina-
tion could block the outside heat exchanger.
Do not install the outdoor unit in areas with a high air content of
oil, saline atmospheres or aggressive gases such as sulphur.
Do not install the outdoor unit close to sources of strong elec-
tromagnetic radiation or in areas where electromagnetic waves
radiate directly towards the electrical box and the components
of the unit. Install the unit as far as possible from these sources
17
PMML0294A_rev.2_02-2014.indb 17
D
E
Center of
gravity
f
c
RAS-FSXN1E
RAS-FSXNH(E)
10/12
14/16
5/6
230
310
215
245
325
230
PMML0294A rev.2 - 07/2014
Insert protection -E- between where the slings touch the upper
protective cardboard packaging of the the unit. The slings must
not touch the unit.
The slings should form an angle of more than 60° -D- with the up-
per part of the unit. The unit should be kept horizontal throughout
the lifting operation. If necessary, tie guide ropes on to prevent the
unit from swinging freely during the lifting process.
Do not apply force to zone -F-.
D A N G E R
No-one should remain in the radius of action of the crane
during the lifting process.
Model
RAS-8FSXN1E
RAS-10FSXN1E
RAS-12FSXN1E
RAS-14FSXN1E
RAS-16FSXN1E
RAS-5FSXNH(E)
RAS-6FSXNH(E)
8-12
RAS-8FSXNH(E)
260
RAS-10FSXNH(E)
RAS-12FSXNH(E)
275
(minimum 3 metres); electronic noise may result in the incorrect
operation of the unit.
C A U T I O N
In areas with high electromagnetic turbulence, a fuse may blow or
the unit stop or an alarm may be triggered. In this case, stop the
system and restart it to remove the alarm.
Make sure that the base of the foundations is flat and strong
enough to bear the weight of the unit.
Install the outdoor unit in an area with enough space around the
unit to permit service and maintenance tasks.
C A U T I O N
The aluminium fins have sharp edges. Take special care to
avoid injury.
The outdoor unit must be installed on rooftops or in areas not
accessible by the user. Only service technicians and mainte-
nance personnel are permitted access to the unit.
a
b
c
d
1,720
950
765
645
465
1,720
950
765
650
465
1,720
1,210
765
615
600
1,720
950
765
645
465
1,720
1,210
765
660
580
(mm)
e
f
335
350
320
335
350
14/07/2014 12:28:08

Werbung