2. Initial commissioning / water tightness test
2. Initial commissioning / water tightness test
Prior to the first commissioning, the system must be filled with clean water until no further
rise of the water level is noticeable. For this purpose, the float must be lifted or removed, as it
will otherwise be sucked down and not be able to rise to the surface on its own.
After filling the system up with fresh water, the float is inserted into the float guide. The float
will stick out approx. 2 to 3 cm above the water surface and must be able to freely float.
If a mixture of oil and water is fed into an empty tank, the separator system will not work
properly and the wastewater would leave the separator system in a state that is cleaned
insufficiently.
The identification plates with chain provided for each separator system must be attached
underneath the concrete cover to the lower edge of the dome.
The taper shaft ring must be covered by the original cover supplied and must be marked
"separator system".
All relevant information, including the serial number from the type approval plate must be
entered on page 2 in this operating manual!
Commissioning must be documented in the commissioning report (please refer to section 4
in the annex). Any claims under the warranty can only be made if the completed
commissioning report is provided!