8.4

Commissioning

WARNING
Risk from electrical voltage!
Electrical connection only by trained and instructed qualifi ed personnel!
8.4.1
Check air gap
 AW-EX/AXC-EX/AXCBF-EX: Check the minimum air gap between blade tip and housing once again (see Table 11).
 DVEX: Check the distance between rotor and nozzle, it must be between 4 mm and 8 mm.
 Only put the fan into operation if the minimum air gap matches your fan's value.
8.4.2

Check direction of rotation

WARNING
Risk from bursting parts
Wear goggles when checking the direction of rotation of the rotor.
 Briefl y switch the fan on and off.
 Check the direction of rotation / direction of conveying. The direction of rotation looking at the rotor always
applies.
 AW-EX: In fans with intake on both sides, the direction of rotation applies looking at the side opposite the connec-
tion wire.
 RVK-EX see Fig. 10
 If the direction is wrong, exchange two phases in order to set the direction of rotation.
Fig. 10:
RVK-EX fan, throughfl ow direction
8.4.3
Switching on
 Switch the fan on.
 Check fl awless function (smooth running)
 Check tight fi tting of the safety components and protective grid.
62