TEST RUN
CAUTION
Failure to perform the test run may result in unit damage, property damage, or personal injury.
Before test run
A test run must be performed after the entire system has
been completely installed. Confirm the following points
before performing the test:
a) Indoor and outdoor units are properly installed.
b) Piping and wiring are properly connected.
c) No obstacles near the inlet and outlet of
the unit that might cause poor performance
or product malfunction.
d) Refrigeration system does not leak.
e) Drainage system is unimpeded and draining
to a safe location.
f) Heating insulation is properly installed.
g) Grounding wires are properly connected.
h) Length of the piping and additional refrigerant capacity
have been recorded.
i) Power voltage is the correct voltage for the
air conditioner
Test Run Instructions
1. Open both the liquid and gas stop valves.
2. Turn on the main power switch and allow the unit to
warm up.
3. Set the air conditioner to COOL mode.
4. For the Indoor Unit
a. Ensure the remote control and its buttons work
properly.
b. Ensure the louvers move properly and can be
changed using the remote control.
c. Double check to see if the room temperature is
being registered correctly.
d. Ensure the indicators on the remote
control and the display panel on the indoor unit
work properly.
e. Ensure the manual buttons on the indoor unit works
properly.
f. Check to see that the drainage system is
unimpeded and draining smoothly.
g. Ensure there is no vibration or abnormal noise
during operation.
5. For the Outdoor Unit
a. Check to see if the refrigeration system is leaking.
b. Make sure there is no vibration or abnormal noise
during operation.
c. Ensure the wind, noise, and water generated by
the unit do not disturb your
neighbors or pose a safety hazard.
6. Drainage Test
a. Ensure the drainpipe flows smoothly. New
buildings should perform this test before
finishing the ceiling.
b. Turn on the main power switch and run
the air conditioner in COOL mode.
c. Check to see that the water is discharged. It may
take up to one minute before the
unit begins to drain depending on the drainpipe.
d Make sure that there are no leaks in any of the
piping.
e. Stop the air conditioner. Turn off the main power
switch and reinstall the test cover.
NOTE: If the unit malfunctions or does not operate
according to your expectations, please refer to the
Troubleshooting section of the Owner's Manual before
calling customer service.