Procedure
1. Drill a hole in the wall at a height of 1.5 m, aligned
centrally to the installation location of the storage
system
2. Move the housing closer to the wall
3. Secure the anti-tilt device with the eye on the
hook. (The hook is not included in the scope of
supply.)
(1)
Anti-tilt device (1)
6.10:
The housing is secured against tipping over.
6.4
Installing and connecting the
batteries
Observe the information on the batteries in the
separate instruction manual provided with the
storage system by the manufacturer Saft: Synerion®
Storage System 4.4kWh to 13.2 kWh