Commissioning
11) Install the fuel cell in the ProCube and screw the fuel cell potion
connector to the Fuel Manager.
12) Connect the exhaust hose to the EFOY fuel cell.
13) Connect the prepared charging cable, the power cable of the Fuel
Manager and the prepared communication cable(s) to the fuel cell.
14) Mount the control panel and fix it to the top-hat rail next to the EFOY Fuel
Manager. Plug the communication cable into the EFOY Fuel Manager.
15) Check that the thermostat is correctly set to 35 °C and has not been
accidentally adjusted during installation.
16) Turn on the main switch of the EFOY ProCube.
Your energy solution is now active.
17) Switch on the EFOY Pro fuel cell manually via the control panel for a test
run (only possible if the battery voltage is below 13.2 V or 26.4 V).
18) Switch on your consumer and connect any installed solar modules or
remove the cover of the solar module.
The EFOY ProCube is now ready for use, the load is active.
19) Check the solar charge controller, the EFOY Pro fuel cell and the
consumer for correct operation.
20) For a version of the ProCube with a built-in router: check whether the
fuel cell can be controlled via the EFOY Cloud.
21) Close and lock the EFOY ProCube.
22) Make sure that the supply and exhaust air ducts as well as the exhaust
hose are not blocked and that the tilt angles are observed.