5. Commissioning, operation
5.2.3 Wiring with cable gland
The wiring should only be carried out in the unpowered state.
Carry out the wiring of the level transmitter as follows:
EN
1. Unscrew the probe head cover using an open-ended spanner.
2. Loosen the union nut of the cable gland .
Removable screw terminal
3. Thread the 2-wire cable into the union nut and tighten (outer diameter: 5 ... 10 mm).
4. Remove the screw terminal .
5. Connect the 2-wire cable to the poles marked with (+) and (–) on the screw terminal .
6. Re-affix the screw terminal . The cable must not have any tension!
7. If required, set reference points (see chapter 5.3.1 "Measuring span on the level
transmitter").
8. Screw the probe head cover back down.