5. Commissioning, operation

5. Commissioning, operation

5.1 Mounting preparation

To protect the pressure gauge from mechanical damage keep it in
the outer carton until installation.
The measuring instrument should only be removed from the
packaging shortly before mounting at the measuring point.
With CIP (cleaning in place) it is recommended to clean the
measuring instrument again after mounting, using the established
process of the operator.
With COP (cleaning out of place) it is recommended to clean the
measuring instrument again before mounting, using the estab-
lished process of the operator.
On removal from the packaging, and during mounting, particular
care must be taken to avoid damage and any mechanical defor-
mation to the diaphragm.
In case of a zero offset, carry out a zero adjustment. See chapter
5.6 "Zero adjustment".
5.2 Installation
Do not damage the diaphragm; scratches on the diaphragm (e.g.
from sharp-edged objects) are the main causes of corrosion.
For sealing, choose appropriate seals.
For flange mounting, only use sealings with a sufficiently large
inner diameter and centre them; contact with the diaphragm leads
to measuring errors.
When using soft or PTFE sealings, observe the instructions of the
sealing manufacturer, particularly with regard to tightening torque
and load cycles.
For installation, in accordance with the fitting and flange standards