Multi-line building entry
MSH FW Basic
6.8
Leakage testing of the MSH FW
1
Remove valve cap (see fig.: 28).
2
Connect test pipe of test pump to valve.
3
Apply a maximum pressure of 0.5 bar via the test
pump.
► After a period of 1 minute, the pressure may not drop
below 0.4 bar.
If the pressure falls below 0.4 bar, please note
the steps described in Section 5.
4
Once the test is complete, the test pressure can be re-
leased at the pump or valve.
5
Measures in the event of pressure dropping below
0.4 bar:
► Check to ensure the valve and pump joint sits firmly.
Pressure still drops:
► Check tightening torque of the screws (see fig.: 16).
Pressure still drops:
► Dismantle and check drill hole diameter.
► Clean core drill hole/wall sleeve.
► Check core drill hole for blowholes in the sealing area
and rework if necessary.