Assembly instructions
4.4
Connection positions
2-way valve, 2-pipe
Heating or cooling
Differential pressure-independent valve,
2-pipe
Heating or cooling
Connection positions
1
Cooling supply (also heating with 2-
pipe systems)
3
Cooling return (also heating)
Heating return
5
5
Pre-commissioning checks
Before initial commissioning, check whether all the necessary conditions have been met so that
the unit can function safely and properly.
Electrical tests
Check whether all lines have been properly laid.
Check whether all lines have the necessary cross-section.
Are all wires connected in accordance with the electric wiring diagrams?
Is the earth wire connected and wired throughout?
Check all external electrical connections and terminal connections are fixed in place and
tighten if necessary.
Check whether DIP switches have been correctly set in accordance with the wiring diagram.
Water-side checks
Check whether all supply and drainage lines have been properly connected.
Fill pipes and unit with water and bleed.
Check whether all bleed screws are closed.
Check leak tightness (pressure test and visual inspection).
Check whether the parts carrying water have been flushed through.
Check whether any shut-off valves fitted on site are open.
Check whether any electrically actuated shut-off valves have been properly connected.
Check whether all valves and actuators are working properly (note permitted mounting pos-
ition).
Condensation water connection
Check whether the condensation tray is free of building rubble.
Check the condensation drain and operation of the alarm signal on the condensation pump.
Check whether the cooling valve switches off in the event of an alarm signal.
Check whether the unit is connected leak-free to the on-site condensation connection.
Check whether the waste water lines are clean and have a sufficient gradient.
Check whether the condensation pump has a working power supply.
6
2-way valve, 4-pipe
Heating and cooling
Differential pressure-independent valve,
4-pipe
Heating and cooling
2
Cooling return (also heating with 2-pipe
systems)
4
Heating supply
Heating return
6
6

Maintenance

6.1
Cleaning the condensate tray
Remove the condensate tray.
Clean the condensate tray.
6.2
Replacing the filter.
CAUTION!
Risk of injury from sharp metal housing!
The inner metal of the casing can have sharp edges.
Wear suitable protective gloves.
Remove the filter.
Vacuum the filter and re-fit it after cleaning.