Personnel requirements - Qualifications
Expertise
The installation of this product requires specialist knowledge of heating, cooling, ventilation, in-
stallation and electrical engineering.
Damage caused by improper installation is the responsibility of the operator or installer. The in-
staller of these units should have adequate knowledge of the following gained from specialist
professional training
Safety and accident prevention regulations
Country-specific guidelines and recognised technical regulations, i.e. Association of German
Electricians (VDE) regulations, DIN and EN standards.
VDI 6022; maintenance personnel must be trained to Category B (possibly Category C) to
comply with hygiene requirements (as required).
2.5
Personal Protective Equipment
Personal protective equipment is used to protect people from impaired safety and health when
working with the unit. The applicable accident prevention regulations at the place of use apply
in all cases.
3
Transport, storage and packaging
3.1
General transport instructions
Check on delivery for completeness and transport damage.
Proceed as follows in the event of visible damage:
Do not accept delivery or only accept with reservations.
Record any transport damage on the transportation documents or on the transport company's
delivery note.
Submit a complaint to the freight forwarder.
IMPORTANT NOTE!
Warranty claims can only be made within the applicable period for complaints.
(More information is available in the T&Cs on the Kampmann website)
IMPORTANT NOTE!
2 people are needed to transport the unit. Wear personal protective clothing
when transporting the unit. Only lift the unit on both sides and not by the pipes /
valves.
IMPORTANT NOTE!
Material damage caused by incorrect transport!
Units being transported can drop or topple over if transported wrongly. This can
cause serious material damage.
Proceed carefully when unloading the equipment on delivery and when
transporting it on site and note the symbols and instructions on the pack-
aging.
Only use the holding points provided.
Only remove packaging shortly before assembling the unit.
4
Installation and wiring
4.1
Requirements governing the installation site
Only install and assemble the unit if the following conditions are met:
Make sure that the wall/ceiling is sufficiently load-bearing to take the weight of the unit.
Make sure that the unit is securely suspended/standing.
Ensure that the airflow can circulate freely.
Provide for adequate space for floor and return water connections on site.
There is a power supply on site.
If need be, provide a condensation connection with a sufficient gradient on site.
4.2
Minimum clearances
min. 2 m
4.3
2 people are needed to install the unit.
min. 2 m
Installation
CAUTION!
Risk of injury from sharp metal housing!
The inner metal of the casing can have sharp edges.
Wear suitable protective gloves.
IMPORTANT NOTE!
Horizontal installation of units!
When installing the units, ensure that they are completely horizontal to ensure
proper operation.
IMPORTANT NOTE!
Avoid draughts!
Consider the occupied zone when installing/suspending the units. Do not expose
people to the direct air flow. Position the unit accordingly and adjust the air out-
let if required.
IMPORTANT NOTE!
Sound insulation
Provide for sound isolation between the and the adjacent building if required.
IMPORTANT NOTE!
Install connections in the de-energised state!
Connections must be installed without tension!
Use a suitable tool to protect terminal nuts from being sheared off and
twisted.
1) Drill four fixing holes (refer to drilling spacings) into the load-bearing ceiling, insert
dowels and fit the appropriate M8 threaded rods.
2) Using M8 fender washers and nuts, fix the threaded rods to the four corresponding fix-
ing brackets on the unit and secure them in place (with self-locking nuts or locknuts).
3) Then dismantle the design panel from the supply lines:
4) open the design panel by pulling on the notches.
5) Push the securing panel inwards to unlock the design panel and open it fully. CAU-
TION: When opening/removing the design panel, do NOT allow the opening angle to
exceed 90° to prevent damage!
6) Unlock the hinges on the right and left by pulling on them and remove the design
panel.
23
KaDeck
Assembly instructions
5