3. Installation of evaporator section, piping and wiring.

The evaporator is installed with 4 attachments to the room. The evaporator is
designed so that there must be 100 mm free space at each side.
Illustration 10 and 11 on the following pages show the placement and
installation of the evaporator.
• The piping for the refrigeration system must be lead through the
evaporator wall or through the ceiling, see illustration 14.
• The drain pipe can be lead through the side panel or the back panel,
see illustrations 15, 16 og 17.
• The wiring is to be lead through the wall panel to the control panel, a
hole Ø45mm must to be drilled, see illustration 18. Pipe and muffs for
wiring lead-through are contained in the box with loose parts.
NB! The length of the wires are fitted to the layout as described.
Procedure:
1. To make handling of the evaporator section easier during mark out and
installation, dismantle the fan door and drip water tray before moving
the evaporator into the room.
2. Place the evaporator in the room, in the way it is to be installed, see
illustration 11.
3. Mark out on the wall, where to drill the holes.
4. Decide how and where drain pipe and wiring are to be placed. See
illustrations 14 - 18 for placement of piping and wiring.
5. Mark out where to drill holes for connections.
6. Remove the evaporator and drill the holes.
7. Move the evaporator in place and attach it as shown in illustration 12.
8. Piping, wiring and drain pipe can now be installed. For installation of
control panel, see separate description.