5.1.9 Lubricating and cleaning the screw and nut screw

Every 250 cycles, clean
and lubricate with
silicone grease the inside
of the threaded bushing
"A" located on the door .
Never use hydrochloric acid or detergents containing chlorine to clean any part of the autoclave.

5.1.10 Clean the feed tank

This must be carried out by qualified technicians.

5.2 Annual maintenance

After every 1000 cycles, or one year after installation, a reminder message appears to perform maintenance.
Annual maintenance can only be carried out by a FARO qualified technician from the FARO Technical Sup-
port Service network.
The maintenance consists of replacing, cleaning and checking some parts, as indicated in the relative table.
5.1.10 Clean the feed tank
The work consists of the following:
This must be carried out by qualified technicians.
Replace:
- porthole seal
5.2
Annual maintenance
- bacterial or Bio X filter
On reaching cycle no. 1000, a message appears, reminding you to carry out maintenance.
- chamber filter
Annual maintenance can only be carried out by a FARO qualified technician from the FARO
- water filter
Technical Support Service network.
The maintenance consists of replacing, cleaning and checking some parts, as indicated in the
- vacuum pump membrane kit (if necessary)
relative table.
Check:
The work consists of the following:
- Safety valve check
Replace:
- Leakage current check
- porthole seal
- Hose checks: hose performance does not change until they physically break, in which
- bacterial or Bio X filter
case they do not work. Only replace them with FARO spare parts.
- chamber filter
- water filter
When finished, the qualified technician will issue a certificate stating that the annual autoclave maintenance
- vacuum pump membrane kit (if necessary)
was carried out.
Comply with the intervals specified or indicated in this manual and in the additional sheets. Only use ORIGI-
NAL SPARE PARTS. Failure to comply will void the equipment warranty.
5.3

Periodic process effectiveness and safety checks

5.3 Periodic process effectiveness and safety checks
Operation
Vacuum Test EN 17665
Bowie & Dick Test 17665
Helix Test EN 17665
Protective earthing continuity
Insulation test
Casing leakage current
Initial validation EN 17665
Periodic validation EN 17665
Safety valve check
Before proceeding with the operations indicated above, always switch off
the main switch (5 Fig. 1) and make sure that the chamber is cold.
Before proceeding with the operations indicated below, always switch off
Never use hydrochloric acid or detergents containing chlorine to clean any part of the autoclave.
the main switch (1 Fig. 1) and make sure that the chamber is cold.
Never use hydrochloric acid or detergents containing chlorine to clean any part of the autoclave.
ANNUAL MAINTENANCE
Check:
Inserire a pag. 51 capitolo 5.1.9
5.1.9 Lubrificazione e pulizia vite e boccola filettata
A
Before first
Daily
use
Clean screw "B" on the front panel
using a soft cloth.
                                                   
Frequency
Annually
Every two
years
                                                  
B
69 69