10.2 Checklist for unit installation

Checked performed
Check unit for damage on delivery
19" slide in resp. rack horizontal adjusted
No remains of packaging in the
CoolServe
All installation tools removed
Cable entries into the rack
unit correct and air-tight
Cable connections checked
Chilled water connection does not leak
Pressure test performed
Chilled water network bled
Chilled water flow rate adjusted
Condensed water pipe clear
Chilled water system odour trap in order
Heat exchanger tray connected to
condensed water pipe
Fan function checked
All front panels closed
(separation of air flows)
.............................................
Place:
CoolServe
Completed
(After completion confirm
)
with signature
........................................
Date:
01_998_345_0_a
Comments
....................
Signature
Checker