Installation
5
Installation
5.1
Preparing for installation
Check the following points:
• Machine freely accessible from all sides
• Do not close ventilation grids and holes
• Sufficient room for installing and removing pipes and for maintenance work, particularly for installing and
dismantling the machine
• No external vibration effects
• Do not suck any hot exhaust air from other machines into the cooling system.
5.2
Installation
Property damage caused by improper installation!
Improper erection and installation can damage the machine.
Ø The machine may only be operated when it is set up horizontally.
(Max. inclination: 10 ° in all directions)
Ø The machine must be screwed to the bearing surface to secure it against tipping and
slipping.
Ø The bearing surface must be plane and even.
Ø The bearing surface must be designed to be able to carry the weight of the machine.
Ø The bearing surface must be at least the same size as the machine.
An output reduction is noticeable when installed at more than 1000 m above sea level. In this
case, please contact us.
It is possible to install the machine on a firm base without anchoring. When installing on a sub-
structure we recommend fixing with flexible buffers.
16
|
www.gd-elmorietschle.com © Gardner Denver Schopfheim GmbH, Gardner Denver Deutschland GmbH
Prematic AG, Märwilerstrasse 43, 9556 Affeltrangen www.prematic.ch
NOTICE
Tel. 071 918 60 60, Mail: v-g@prematic.ch
loading

Diese Anleitung auch für:

V-vgd 16V-vgd 21