8 Decommissioning
8.1

Temporary decommissioning

If the machine is not used for a longer period of time (starting at about 4 weeks) the following measures
have to be taken by a service technician (for hygienic reasons):
Turn off the machine off and let it cool down / warm up for 24 hours.
Drain the boiler.
Empty the product canisters (also turn over the crank filler (spiral) by hand).
Carefully clean the machine (see chapter Maintenance).
If it turns out in retrospect that the machine has been out of commission for a longer period of time, the
following has to be done by a service technician:
Check all components for hygiene and damage.
If needed replace dirty or damaged items.
Before commissioning again, see paragraph 3.6.
8.2
Disposal
If the machine is to be disposed of, the following has to be done by a service technician:
Turn off the machine off and let it cool down up to 24 hours.
Drain the boiler.
Empty the product canisters (also turn over the worm drive by hand).
Carefully clean the machine (see chapter Maintenance).
Make sure the machine is complete.
Hand in the machine.
If the machine is to be replaced by a new machine from Veromatic International B.V. the old machine will
be taken back by the supplier for recycling.
For devices of Veromatic International BV a disposal fee has been paid. You can ask your supplier to pick
up the machine and take it to specially allocated return stations. The return station will ensure that the
machine will be recycled in such a way as to cause the smallest possible burden for the environment.