The shut-off frame (13) is set at
The hex nut (15) on the shifting rod (16) is approached to the lever (14) of the shut-off frame. Secure the nut.
Set the adjusting screw (18) to the shut-off frame (13) at the value of "Y" and secure it.
12.1 TESTING THE SHUT-OFF DEVICE
Put the shut-off frame (13) against the PE-pipe (last layer).
Move the shut-off lever (9) to position "PE-pipe retraction".
Pull the shut-off frame (13) to shut-off position (=
The shut-off lever must jump to shut-off position!
26
X
mm off the reel (17) ( see below table ).
Machine
Smart RAIN
17
13
15
X
X
mm
45
mm off the reel).
Betriebsanleitung für Smart RAIN
Y
mm
75