Herunterladen Inhalt Inhalt Diese Seite drucken

Preparing The Dc Connections; Preparing The Data Connection Cable; Connecting The Inverter And Switching On The Ac Power; Initial Commissioning Of The Inverter - Solar Frontier PowerSet 6.0-170-3p Bedienungsanleitung

Inhaltsverzeichnis

Werbung

Verfügbare Sprachen

Verfügbare Sprachen

Only for the Turbo 1P inverter:
1 Connecting cable between N and PE with the connection point inside the AC plug
2 External conductor L1
3 External conductor L2
4 Connecting cable between N and PE with the connection point in the junction box
5 Casing of the AC plug
6 Junction box
L
L
2
3
100 - 127 V
N
100 - 127 V
L
1
Only for the Turbo 3P1 / 3P2 inverter:
Wire the AC plug provided as described in the following Figure.
1
Phase 1
2
Phase 2
3
Phase 3
4
As the inverter is protection class II,
the PE protective conductor has no
function and need not be connected.
5
Neutral conductor
5.4.4

Preparing the DC connections

Danger
Risk of death by electrocution!
For Multi-Contact MC4 DC connections, the matching Amphenol Helios H4
mating parts must be attached to the DC cable (mating parts are included in the
delivery). Observe the warning notes in 5.4.1.
Use the SunClix connectors provided to maintain the specific protection class.
Attention
Danger of damage to the inverter and modules.
Connect the mating parts matching the DC connectors to the DC cable with the
correct polarity.
Connect the Amphenol Helios H4 mating parts to the DC cable as per the instruc-
tions in section 5.3.2.
5.4.5

Preparing the data connection cable

If a data connection is required, use a standard RJ45 cable (patch cable, Cat5) or,
if necessary, construct an alternative data connection cable.
5.4.6

Connecting the inverter and switching on the AC power

Danger
Risk of death by electrocution! Observe the warning notes in 5.4.1.
Attention
Maintain a minimum clearance of 200 mm (7.87 in) between the data connection
cables (RS485/Ethernet) and the DC /AC cables to prevent data transmission
interference.
Figure 27
Connecting N and PE
in the AC plug (top)
or distribution box (bottom)
L
2
N
Figure 28
External conductor voltages
in 2 and 3 phase grids with
100 V ...127 V
L
1
Figure 29
1.
If necessary, establish a data connection:
- Connect the inverter and master using the data connection cable.
- Switch on the termination (slide switch) at the last inverter.
2.
Push the Amphenol Helios H4 opposing connector of the DC cable firmly
into the DC connection of the inverter until it audibly clicks into place.
3.
Insert the AC plug into the socket on the inverter until it audibly clicks into
place.
4.
Switch on the AC line circuit breaker. The start page for initial commissioning
is shown on the display.
5.
Perform initial commissioning and switch on the DC supply, as described in
5.4.7 and 5.4.8.
5.4.7

Initial commissioning of the inverter

Before connecting the PV system to the grid, ensure that the complete system
has been checked, tested and approved in accordance with the relevant
regulations.
Depending on local regulations, only accredited personnel may connect the
PV system to the grid and commission it.
Function
Conditions for starting initial commissioning
Initial commissioning starts automatically when at least the AC connector has
been installed and switched on as described previously. If initial commissioning is
not fully completed, then it starts anew the next time the device is switched on.
Guided initial commissioning
Initial commissioning is a guided procedure that sets the following information:
PowerSet
Display language
Date / Time
Country
Reactive power characteristic curve (if prescribed for the selected country)
Setting the country
The following applies when setting the country:
The set country must always be the same as the country where the inverter is
installed. This causes the inverter to load the prescribed grid parameters for the
selected country. More information on this is provided in the table of countries
in section 10.4.
The country can only be set once!
If you have selected the wrong country, contact your installer or Solar Frontier.
If you cannot select your country on the inverter, contact your installer or Solar
Frontier.
The country setting does not affect the language used on the display. The
display language is set separately.
Operation
Starting initial commissioning
√ The check list for initial commissioning is
displayed.
• The PowerSet entry is selected.
• The checkboxes are not selected.
Advices
• When a check list item is called up the corres-
• The following items are only displayed if the
• – Reactive power characteristic curve
• Initial commissioning is completed by calling
• Finish can only be performed when all other
9
ponding checkbox is automatically selected.
use of a reactive power characteristic curve
is prescribed for the country selected in the
Country item:
(reactive power characteristic curve type)
– Number of nodes
1)
– Node 1
1)
– Node 2
1)
– Node n
1) 2)
– Display characteristic curve
1)
: Only displayed for reactive power characte-
ristic curve type Enter characteristic curve.
2)
: Only displayed if Number of nodes has
been set to a value > 2.
up the Finish item.
checkboxes are selected.

Werbung

Inhaltsverzeichnis
loading

Verwandte Produkte für Solar Frontier PowerSet 6.0-170-3p

Inhaltsverzeichnis