4.11 System startup and shutdown
Startup procedure
① After connecting the battery cables, press the air switch button on the high-voltage control
box to turn OFF to ON.
②Press the start button and wait for the screen to light up.
③Complete boot
Shutdown procedure
①Press the start button again and wait for the screen to go off.
②Press the air switch button ON the high pressure control box and set the "ON" to the "OFF"
position.
③Complete shutdown
Description of external circuit breakers between inverter and battery system
Turn on the circuit breaker after the battery pack is
started and turn off the circuit breaker after the battery
pack is closed.