Commissioning several net-
worked units
System with several Schüco
inverters
Commissioning master
IPE 030 - 033 CN 05
Master
Before commissioning, all units must be interconnected via the CAN bus interface.
See the chapter on networking Schüco inverters via CAN bus.
Switch on all units following installation. Start commissioning with the unit you selec-
ted as the master.
1. During initial start-up the following appears on the display:
Start commissioning with
2. To do this, select the language in selection menu with
selected language with
3. Select the country in the selection menu with
4. Confirm the country of installation with
NOTE
The inverter only starts feeding current into the grid once the country has been se-
lected.
5. Select "Master" in the selection menu with
Confirm with
.
NOTE
The other units in the CAN network are automatically configured as slaves.
Slaves
.
.
/
.
/
.
Commissioning
/
. Confirm the
.
75