When correctly positioned, the basic unit is 235 mm above
11
the unfi nished fl oor after concreting.
The system allows shortening of the basic unit to the
later fl oor superstructure or the fi nished fl oor level by up
to 155 mm at a later stage (see Fig.: 17).
Legend for Fig.: 17
1
Unfi nished fl oor level
IMPORTANT!
No sealing due to incorrect preparation of
installation!
Incorrect preparation can result in damage.
• Please ensure that the shortening area (the black
compensation frames) is within the area of the
fi nished fl oor level (important in the case of
fl oor structures which are higher than 235
mm and smaller than 80 mm) (see Fig.: 18).
Legend for Fig.: 18
1
Shortening area
2
Insulation
3
Overhang max. 50 mm
4
Finished fl oor height
5
Unfi nished fl oor height
After fi xing the height of the MSH Basic-FUBO-E-SR4 (basic
12
unit) and while fi lling with sand, the level provided on the
cap can be used to align the position (see Fig.: 19).
IMPORTANT!
No sealing due to incorrect preparation of
installation!
Incorrect preparation can result in damage.
• While fi lling with sand, check the spacing from
the batter board and the vertical position of the
component and adjust as necessary.
• Spacing between inner wall side and outside of
basic unit: 5 cm.
34
Art. Nr.: 5090032065
Rev.: 03/2018-09-25
1
1
Fig.: 18
EN
Fig.: 17
4
5
2
3
Fig.: 19

Werbung

Kapitel

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Msh basic-mbk-r4

Inhaltsverzeichnis