Master/Slave operation

The master/slave operation enables that several devices can be synchronized and controlled by one master
device.
On the rear panel of the device you can find an XLR jack and an XLR plug, which can be used for
connecting several devices.
Choose the device which is to control the effects. This device then works as master device and controls all
other slave devices, which are to be connected to the master device via a DMX-cable. Connect the OUT jack
with the IN plug of the next device.
Set all Slave devices to the Slave Mode. (See instructions under Control Board).

Connection with the mains

Connect the device to the mains with the enclosed power supply cable.
The occupation of the connection-cables is as follows:
Cable
Pin
Brown
Live
Blue
Neutral
Yellow/Green
Earth
The earth has to be connected!
If the device will be directly connected with the local power supply network, a disconnection switch with a
minimum opening of 3 mm at every pole has to be included in the permanent electrical installation.
The device must only be connected with an electric installation carried out in compliance with the IEC-
standards. The electric installation must be equipped with a Residual Current Device (RCD) with a maximum
fault current of 30 mA.
Lighting effects must not be connected to dimming-packs.

Connection between devices

On the side panel, there is a socket (Power Out). Connect the output with the mains input of the next fixture
until all fixtures are connected.
Please note: A maximum of 8 devices may be linked together. After every 8 devices, the fixtures must have
International
L
N
a renewed connection with the power mains.