Electrical Connection; Start-Up; General Information; Preparation - Buderus WPL 180ARH Montage- Und Gebrauchsanweisung

Werbung

Verfügbare Sprachen

Verfügbare Sprachen

6.3

6.3 Electrical Connection

A standard four-core cable is used for connecting the heat pump
to the power supply.
The cable must be provided by the customer. The conductor
cross section is selected in accordance with the power consump-
tion of the heat pump (see Appendix Device Information) and the
applicable VDE (EN) and VNB regulations.
An all-pole disconnecting device with a contact gap of at least
3 mm (e.g. utility blocking contactor or power contactor) as well
as a 3-pole circuit breaker with common tripping for all external
conductors must be installed in the power supply (tripping current
in compliance with the Device Information).
Ensure that the incoming supply has a clockwise rotating field
when connecting multiphase devices.
Phase sequence: L1, L2, L3.
ATTENTION!
Ensure that there is a clockwise rotating field: Operating the
compressors in the wrong rotational direction could cause damage to the
compressors.
The control voltage is supplied via the heat pump controller.
The heat pump controller has a 230 V AC-50 Hz power supply.
Connect the controller in compliance with its own operating in-
structions (16 A fuse).
The control line (not included in scope of supply) is connected to
the heat pump controller using the two rectangular plug connec-
tors. Use the plug connector located on the base of the heat
pump adjacent to the cable gland in the base plate. More de-
tailed information can be found in the operating instructions of
the heat pump controller.
For detailed information, see Circuit Diagrams in the Appendix.
E-6
7

Start-up

7.1 General Information

To ensure that start-up is performed correctly, it should only be
carried out by an after-sales service technician authorised by the
manufacturer. This may be a condition for extending the guaran-
tee (see Warranty Service).

7.2 Preparation

The following items need to be checked prior to start-up:
The heat pump must be fully connected, as described in
Chapter 6.
All valves that could impair the proper flow of the heating
water in the heating circuit must be open.
The air intake and air outlet paths must be clear.
The ventilator must turn in the direction indicated by the ar-
row.
The settings of the heat pump controller must be adapted to
the heating system in accordance with the controller's oper-
ating instructions.
Ensure the condensate outflow functions properly.

7.3 Procedure

The heat pump is started up via the heat pump controller. Adjust-
ments should be made in compliance with the instructions.
If an overflow valve is fitted to maintain the minimum heating
water flow rate, the valve must be adapted to the requirements of
the heating system. Incorrect adjustment can lead to faulty oper-
ation and increased energy consumption. We recommend carry-
ing out the following procedure to correctly adjust the overflow
valve:
Close all of the heating circuits that may also be closed during
operation (depending on the type of heat pump usage) so that
the most unfavourable operating state - with respect to the water
flow rate - is achieved. This normally means the heating circuits
of the rooms on the south and west sides of the building. At least
one heating circuit must remain open (e.g. bathroom).
The overflow valve should be opened far enough to produce the
maximum temperature spread between the heating flow and re-
turn flow listed in the following table for the current heat source
temperature. The temperature spread should be measured as
close as possible to the heat pump. The heating element of mono
energy systems should be disconnected.