DANGER
Risk of injury! The main switch of the vacuum cleaner is to be
switched off or the Cekon plug must be unplugged while carrying
out any repairs or maintenance jobs.
Time
Activity
daily
Check hand-
spray gun
Check high pres-
sure hoses
Check the con-
necting line with
mains plug
weekly or after 40
Check oil level
operating hours
Check oil level
Cleaning the
sieve
monthly or after
Check pump
200 operating
hours
Check for inter-
nal deposits
Cleaning the
sieve
after 500 - 700 op-
Replace
erating hours
half-yearly or after
Oil change
1000 operating
hours
check, clean
Replace the hose Hose to exhaust pushbutton
annual
Safety check

Maintenance and care

Maintenance schedule

Assembly affected
Hand spray gun
Outlets, hoses towards working
machine
Electrical connection with plug/
socket
Oil tank at the pump
Oil tank at the pump
Sieve in water inlet
High-pressure pump
Entire plant
Sieve in the water shortage
safeguard
Electric igniter, ionisation elec-
trode
High-pressure pump
Entire plant
switch
Entire plant
EN
Performance
Check whether the hand-spray gun closes tightly
without any leaks. Check the protection mecha-
nism against accidental switching. Replace de-
fective hand-spray guns.
Check hoses to see if there are damages. Re-
place defect hoses immediately. Danger of acci-
dent!
Check the connecting line with mains plug for
damages. If the power cord is damaged, please
arrange immediately for the exchange by an au-
thorized customer service or a skilled electrician.
If the oil is milky, it needs to be replaced.
Check oil level of the pump. Refill oil if required
(Order no. 6.288-016)
See section "Clean sieve".
Check the pump for leaks. If the leakage is more
than 3 drops per minute, call Customer Service.
Operate the machine using the spray pipe without
the high pressure nozzle. If the operating pres-
sure on the manometer of the machine increases
to more than 3 MPa, then the plant needs to be
decalcified. The same is applicable when an op-
erating pressure of more than 0.7 - 1 MPa is de-
tected while operating the machine without high
pressure pipe (water comes out freely at the high
pressure outlet).
See section "Clean sieve".
Replace electric igniter and/or the ionisation elec-
trode.
Drain off oil. Fill in 1 l new oil (Order no. 6.288-
016). Check oil level in the oil tank.
Visual inspection of the plant, check high pres-
sure connections to see that they are not leaking,
check that the over-flow valves are not leaking,
check high pressure hoses, check pressure
tanks, remove calcium deposits from the heating
coil, clean/ replace ionisation electrodes, adjust
burner.
Install new hose.
Perform a safety inspection as per the applicable
national rules and regulations for liquid spray jets
of the respective country.
9
-
of whom
Operator
Operator
Operator
Operator
Operator
Operator
Operator
Operator
trained in de-
calcification
Operator
Customer
Service
Operator
Customer
Service
Customer
Service
Technical ex-
pert
31

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Hds 9/16-4 st gasHds 12/14-4 st gasHds 12/14-4 st gas lpg

Inhaltsverzeichnis