Checking the scope of delivery

Check the contents of the package.
Validity: VPS R 100/1 M
Quantity
Description
1
Buffer cylinder
1
Bag with three feet, three washers and six
nuts
2
Wall-fixing strip
4
Pin for securing the wall-fixing strip to the
cylinder
1
Lower cover, which must be attached when
securing the cylinder to the wall
3
Pin for securing the cover, washer and cover
for the pin
1
Cylinder dry pocket
1
Stuffing box
6
G1"1/2 plug + seal
1
Documentation records
Validity: VPS R 200/1 B
Number
Designation
1
Buffer cylinder
1
Bag with three feet, three washers and six
nuts
2
Sensor pocket
2
Stuffing box
6
G1"1/2 plug + seal
1
G3/4 plug for draining the cylinder
1
Enclosed documentation
4.3
Dimensions of the product and the
connections
4.3.1
Cylinder with 100-litre capacity
Ø563
256
18
4.3.2
Cylinder with 200-litre capacity
Ø600
4.4

Minimum clearances

200
Comply with the clearances that are shown in the plan.
Ensure that the water-supply connections can be ac-
cessed for checks.
Leaving additional space around the product is helpful for the
installation and for maintenance work.
4.5

Clearance from combustible components

Ensure that no highly flammable parts come into contact
with the components as these may reach temperatures of
over 80 °C.
Ensure that there is a minimum clearance between the
highly flammable parts and the hot components.
Minimum clearance: 200 mm
Operating and installation instructions 0020244064_02
200
Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Vps r 200/1 b00100214560010021457

Inhaltsverzeichnis