6.2
Commissioning the product
 Verify that the product has been properly mounted and electrically con-
nected.
1. Apply voltage via the on-site mains fuse.
- The green LED at the control unit lights.
The specialised company certifies the installation, commissioning and test of
the product (see "Certification of specialised company (as per AwSV)").
6.3
Performing the function test
Perform the function test at the following occasions:
After each commissioning
After each alarm
Once per year during maintenance
Have the function test performed and documented by a specialised company.
A test report on the function test must be created and kept with the system
documentation.
Basic function
Collect the escaping leak detection fluid using a suitable collection recepta-
cle.
1. Place a collection receptacle below the test valve.
2. Open the test valve.
- The leak detection fluid must escape at a flow rate of at least 0.5 l/min.
3. Close the test valve.
4. Refill the collected leak detection fluid into the container for leak detection
fluid.
Commissioning
LAG-14 ER