Herunterladen Inhalt Inhalt Diese Seite drucken

Technical Data; Installation Instructions - Honeywell EEM400-D-MO Montage- Und Bedienungsanleitung

65 a-wirkenergiezähler 3-phasig mit modbus schnittstelle, pic. 1
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen

Verfügbare Sprachen

Assembly and operating instructions Type EEM400-D-MO
65 A Three-phase active power energy meter with Modbus interface, Pic. 1
Description
Energy meter with RS-485 Modbus interface enables the
reading of all relevant data like meter reading, electricity,
voltage and power (active and reactive).

Technical data

Connection
Pic. 2
diagram
Dimensions
Pic. 3
Accuracy class
B according to EN50470-3,
1 according to IEC62053-21
Reference, Maxi-
I
= 10 A, I
ref
mum, initial current
Operating voltage
3 × 230/400 V
Tolerance –20 %/+15 %
Counting range
00 000,00...999 999,0 kWh
LED-Ouptut
1000 Imp/kWh
Connections
Conductor cross-section 1,5...16 mm
main circuit
screwdriver pozi no. 1, slot no. 2,
torque 1,5...2 Nm
Connections
Conductor cross-section max. 2,5 mm
Control circuit
screwdriver pozi no. 0, slot no. 2,
torque 0,8 Nm
Operating
–25... +55 °C (noncondensing
temperature
according standard EN50470)
Environment
Mechanical M2
Electromagnetic E2
Indicating elements (Pic. 4)
T1total (kWh)
Shows total consumption Tariff 1
T1part. (kWh)
Shows partial consumption for
Tariff 1, this value is resettable
T2total (kWh)
Shows total consumption Tariff 2
T2part. (kWh)
Shows partial consumption for
Tariff 2, this value is resettable
Shows the instantaneous power
P (kW)
per phase or all phases
Shows the voltage per phase
U (V)
Shows the current per phase
I (A)
Shows the unit kWh when the
kWh
consumption is displayed
For P-, U-, I- or Error display, the
L1 / L2 / L3
corresponding phase is displayed
In case of missing phase or wrong
Error
current direction. The corresponding
phase is additionally displayed.
Notes before connecting
1. Do not connect L1, L2 or L3 to N
2. In order to avoid moisture in the meter due to
3. N must always be connected.
Attention!
These devices must only be installed by a professional
electrician, otherwise there is the risk of fire or the risk of
an electric shock.
Operation of the LCD display
= 65 A, I
40 mA
max
st =
See page with LCD menu navigation
, 50 Hz
AC

Installation instructions

,
2
The three-phase energy meter can be attached to a 35 mm
rail (EN60715TH35).
The meter can be used only in installation cabinets.
,
2
Declaration of Conformity CE
We, Honeywell Technologies Sàrl, 1180 Rolle, herewith
declare, on our own responsibility that the product:
which this certificate refer to, are in accordance with the
directive 2004/22/EG (MID) and the following standards:
Murten, 30.04.2013
Conformity Assessment Body:
Signed:
condensate build-up, acclimatise the meter at room
temperature for about half an hour before connecting.
EEM400-D-MO-MID
EN50470 parts 1 and 3 (electronic meter), of
October 2006.
METAS-Cert, Nr. 1259
CH-3003 Bern-Wabern
Urs Tanner, Site Quality Leader
English

Werbung

Inhaltsverzeichnis
loading

Inhaltsverzeichnis