6. Commissioning, operation
6.9 Exiting the furnace
The sensor should exit the furnace as per installation requirements. MI cable must follow
best practices for routing.
WARNING!
EN
Ensure the cable does not pass through direct flame.
6.9.1 Fixed exit
Assemble the process neck extension as per the installation.
Install and tighten compression fitting to manufacturer's specifications, if included.
WARNING!
Do not place compression fitting on the thermocouple transition.
Assemble instrument neck extension as per the installation requirement.
If applicable, attach connection head.
Route sensor to termination location and complete electrical connection.