8

Commissioning

Before putting the system into operation, a functional test of the actuator must be carried out.
Requirements
The actuator is not connected to power.
 Make sure that the supply voltage matches the details on the type plate.
 Make sure that the actuator is connected properly.
 Check fuse on customer side: Max. 16A Trip Curve: C, Standards Compliance: cUL489,
CSA C22.2 No. 5.1, IEC 60947-2
 Check that the valve position matches the position indicator of the actuator.
 Make sure that actuator and valve are connected correctly and tightly with each other.
Using the emergency manual override hand crank, the valve can also be opened or
closed without power, see Chapter "Insert the emergency manual override hand
crank".
8.1

Putting the actuator into operation

Too high current peaks during the actuator is switched on due to charging of the mains
capacitor!
Danger of malfunction.
Connect and operate the actuator as per wiring diagram, see Chapter "Wiring diagram
EA15".
4. Connect the actuator to appropriate power.
The ready for operation signal appears.
5. If necessary, make further settings, e. g. invert the LED color assignment, adjust the
end positions and set the heating element, see Chapter "Operation".
In case of a malfunction, an error message is indicated at the 7 segment display, see
Chapter "Fault message indicator".
Commissioning