8. Move the protective housing aside.
The ball valve is now accessible
5.4

Pressure testing the inner pipe

WARNING
Risk of injury and/ or damage due to pressure testing!
Using hazardous media for pressure testing may put the installation at risk
and cause physical damage or bodily harm in case of leakage.
 The pressure test must be performed using non-harzardous media (e.g
water) and with due care and attention in handling.
 Please pay attention to the instructions in the user manual included for
ball valve type 546.
CAUTION
Risk of material damage or risk of injury!
Overstraining due to exceeded maximum pressure The test pressure of an
assembly may not exceed 1.5 x PN (maximum of PN + 5 bar). The component
with the lowest PN determines the maximum allowed test pressure in the
performance section.
 Prior to and during the pressure test, the assemblies and connectors
must be checked for leak-tightness. Record result.
1. The pressure test must be performed with water or another non-hazardous
medium. See DVS 2210-2 with reference to DVS 2210-1, Suppl. 2.
2. After the leak test: remove the test medium.